问题描述:
[单选]
A planned order consists of a suggested order quantity, a start date and a finish date. 一张计划订单包含建议的订单数量,开始日期和结束日期
A.Maybe
B.FALSE
C.TRUE
D.Don’t Know
参考答案:查看无
答案解析:无
☆收藏
答案解析:无
☆收藏
上一篇:Master production schedule (MPS) is used to plan parts that greatly influence company profits or take up critical resources.主生产计划(MPS)用于计划那些对公司利润影响很大和至关重要的物料
下一篇:The demand plan will be managed as PIR (Planned Independent Requirement) 需求计划会以PIR(计划独立需求)的形式进行
- 我要回答: 网友(216.73.216.96)
- 热门题目: 1.叉车人员需要负责的责任区域有 2.对于整顿,应当将电脑网线、电 3.对于仓库及储物间 ,实行定置