问题描述:
[单选]
重要材料需要运输供应商。如果该材料不能按时交付,项目预算将严重受到影响。为降低这个风险,项目经理购买了保险。项目经理采用了哪一种消极风险策略?Important materials require transportation suppliers. If these materials are not delivered on time, the project budget will be severely affect To reduce this risk, the project manager has subscribed insurance. Which negative risk strategy does the project manager use?
A.规避 Avoidance
B.接受 Acceptance
C.减轻 Mitigation
D.转移 Transfer
参考答案:查看无
答案解析:无
☆收藏
答案解析:无
☆收藏
上一篇:在一个季度末,项目发起人要求进度报告中包含一个指标,以确定项目是否将按时完成或将延迟多长时间。项目经理应该在这份报告中包含哪个指标?At the end of the quarter,a project sponsor requests that the progress report include a metric to determine if the project will be finished on time or how long it will be delay.What should the project manager include in this report?
下一篇:A Water is the root(根本)of our life. No one can live without water. On the one hand, although about seventy-two percent of the world is covered with water, about ninety-seven percent of it is sea water or salt water, so the water we can drink is really limited. On the other hand, because the number of people in the world is becoming larger and larger, more and more drinking water is needed. We should do something to save water in our everyday life. Try to fix broken taps or leaky(漏的) toilet at your home. Turn off the tap as much as you can-don"t use running water to wash your hands, wash vegetables and so on. Never pour away waste water because you can use it to do other things, such as watering a plant or a garden. Do not often water your lawn(草坪). As a general rule, lawns only need watering every 5 to 7 days in summer and every 10 to 14 days in winter. Stop taking long baths and have short showers.1.People can only drink about()of the water on the earth.
- 我要回答: 网友(3.142.131.24)
- 热门题目: 1.星辰(不含零售云、电商云)与 2.购买星辰ISV专版开发工具包 3.应用市场下单操作,以下说法正